A Manitowoc 16000 crawler crane and a Grove GMK5120B all-terrain crane were utilized to erect the 2.5 MW turbine.The first task of the project was off-loading and erecting the four tower sections from their delivery trucks. The sections were lifted and walked into position by the Model 16000, with the GMK5120B providing tailing support. Each section weighed approximately 70 tons.